House wrap missing behind old siding in Nepean, must it be added?

Answer from Siding IQ

When siding is removed and new siding goes on, the 2024 Ontario Building Code (Div. B, 9.27.3.2. and 9.27.3.3.) requires at least one layer of sheathing membrane conforming to CAN/CGSB-51.32-M beneath the new cladding, with joints lapped not less than 100 mm and upper sheets overlapping lower sheets where the membrane runs horizontally. The absence of wrap behind the old siding does not change that: the new installation is new work, and new work is done to the current Code.

There are two situations where the membrane requirement shifts. If non-wood-based rigid exterior insulating sheathing is installed with joints sealed or lapped and detailed to drain, or if the sheathing has an integral membrane, the separate wrap layer is not required under 9.27.3.4. If there is no sheathing at all, two layers of membrane are required instead of one (9.27.3.5.). Once the wall is open, ask the contractor which situation applies; the quote should account for it.

The Code also requires that both a first plane of protection (the cladding itself) and a second plane (the membrane and flashing assembly behind it) be maintained at every wall penetration, including windows, doors, ducts and outlets (9.27.2.2.(4), 9.27.3.1.). Flashing is required at every horizontal junction between cladding elements and at horizontal offsets, and sealant goes between the siding and adjacent window and door frames (9.27.4.). The Code's explanatory notes say a drained space at least 10 mm deep behind the cladding is recommended for walls other than masonry, though no Ontario cladding clause makes that gap a requirement.

A fair quote for this job should spell out, in writing, what it includes for each of these items:

  • the membrane: product, number of layers, how joints will be lapped
  • flashing at every horizontal junction and at openings where required
  • sealant at windows, doors and other penetrations
  • what happens if structural sheathing is found to be damaged or missing once the old siding comes off, and how any additional cost will be agreed before work continues
  • removal of the old siding and disposal, including who arranges it
  • the manufacturer's written installation instructions for the new cladding, and the written warranty
Once the job is done, keep the signed contract, the itemized quote, the manufacturer's warranty documents, and photos taken of the bare wall before the new membrane and siding went on: those records are the clearest evidence of what was done and what was agreed.
Ottawa Siding Contractors

Want this done at your place?

Tell us about your siding and we'll send it to local Ottawa siding contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.

Fields marked are required.

We won't call you. There's no phone box above because we don't ask for one — your estimate comes by email, on your time.

Request received We’ve sent your details to local Ottawa siding contractors. Interested contractors reply by email. A confirmation is on its way to your inbox.

Siding IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.

Ready to Get Quotes?

Find local siding contractors in Ottawa. Free matching, no obligation.

Find a Siding Contractor